Non-Compliance detail


  
Summary
 
Licence number: 5305
Annual Return Start: 06 Dec 2017
Annual Return End: 05 Dec 2018
Date Received: 31 Jan 2019
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
O1- Activities must An EPA inspection found: leaks from chemical dosing lines; bunding capacity less than required; Alum dosing pump outside of the bunded area. The EPA added a PRP to the licence to address these shortcomings. EPA has written to licensee regarding non-compliance and relevant action 1